Reports until 12:20, Thursday 16 February 2012
LHO General
david.barker@LIGO.ORG - posted 12:20, Thursday 16 February 2012 (2244)
MSR and control room upgrades

H1 front end racks were installed into the MSR and populated with computers. The first two of the H2 racks were installed and have front ends installed except those currently running the H2OAT.

Images attached to this report