bubba.gateley@LIGO.ORG - posted 13:23, Friday 16 October 2015 (22587)
Beam Tube Enclosure Joint Repair on the X-Arm
On 10/14 we resumed the repair efforts on the beam tube enclosure 600 meters north of Mid-X. 

Somewhat of a slow start but we managed to clean the joints on 160 meters of enclosure and install metal strips and caulk 120 meters of upper enclosure.   