Reports until 16:24, Tuesday 28 February 2012
H1 PSL
michael.rodruck@LIGO.ORG - posted 16:24, Tuesday 28 February 2012 (2311)
H1 PSL installation

Anteroom frame went up today. The wall against the laser room has not been set up yet, as they need dimensions from the acoustic door first.

Acoustic door shipped today, and is scheduled to arrive early next week (did I say it was going to arrive today? Oops).

Images attached to this report