- HAM6 set, dust counts being watched (even as dust monitors are rebooted by Patrick - Apollo using dirty room for degrouting/drilling of HAM5 - Erecting H1-Electronics Mezzanine Storage - Instrument Air being used by GV6 and GV8 - Venting Y-Beam Manifold swapping flange out - EY: Testing to find rubbing - TMS: Looking for replacement cable, Time Domain Reflectometer - Ken working on instrument wiring at H1 PSL - H1 PSL fan units may come today (Friday) - SEI - set elevations of HAM1 support tubes
At around 12:40 we appeared to have lost the ETMy computer. David went out to EY and then performed a remote reboot to get it back online.
Chris and seismic crew did a reboot to the SEI model.