LHO General
jonathan.berliner@LIGO.ORG - posted 13:01, Friday 02 March 2012 - last comment - 15:59, Friday 02 March 2012(2340)
Mid-Day Ops Log
- HAM6 set, dust counts being watched (even as dust monitors are rebooted by Patrick
- Apollo using dirty room for degrouting/drilling of HAM5
- Erecting H1-Electronics Mezzanine Storage
- Instrument Air being used by GV6 and GV8
- Venting Y-Beam Manifold swapping flange out
- EY: Testing to find rubbing
- TMS: Looking for replacement cable, Time Domain Reflectometer
- Ken working on instrument wiring at H1 PSL
- H1 PSL fan units may come today (Friday)
- SEI - set elevations of HAM1 support tubes
Comments related to this report
corey.gray@LIGO.ORG - 15:59, Friday 02 March 2012 (2341)

At around 12:40 we appeared to have lost the ETMy computer.  David went out to EY and then performed a remote reboot to get it back online.

Chris and seismic crew did a reboot to the SEI model.