H1 PSL
michael.rodruck@LIGO.ORG - posted 17:00, Friday 02 March 2012 (2347)
H1 PSL installation

Electrical work is ongoing - wiring lights, running cables for sensors, etc. AC units now have power, but are not turned on. Next week the acoustic door should arrive, as well as the HEPA units for the clean rooms.