LHO FMCS
bubba.gateley@LIGO.ORG - posted 15:55, Friday 20 November 2015 (23607)
Beam Tube Enclosure Joint Repair on the X-Arm
This report will include this week and last week. We were able to clean the joints, install metal strips and caulk on 360 meters of enclosure.