H2 SUS
betsy.weaver@LIGO.ORG - posted 10:56, Monday 12 March 2012 (2410)
H2 ETMy status
This morning, we finished mounting the cable lacing brackets on the PenRe and the UIM in order to facilitate the non/grounding issues (disassembled brackets last Fri).  After we were done, we observed some pitch in R0 so we had to play more with the brackets and cable routing.  We've left the suspension fully hanging (free).  TMS is up next to remove EQ hardware, followed by SEi for unlocking, then on to TFs.