TITLE: Dec 10 DAY Shift 16:00-00:00UTC (08:00-16:00 PDT), all times posted in UTC
STATE Of H1: Observing
SUPPORT: Sheila, Hugh,
INCOMING OPERATOR: Nutsinee
SHIFT SUMMARY:
A combination of very high microseism (≥1µm/s) and high winds, for most of the day, made it less than possible for re-locking.
Sheila did a lot of work on COMM gain stepping during less than desirable conditions
Hugh changed a Z axis Stage 1 blend at EX on Rich Mittleman’s advice
Looks like an IA is in order for the next shift.
ACTIVITY LOG:
16:43 Out of Observing while Livingston investigates noise. Robert is using the time to do injections.
17:09 Floor covering folks are on site. (OSB carpeting).
17:15 another carpet installer on site
17:27 Robert is going to wait for the carpet installers to unload pallets behind the corner station with the forklift before starting his injections.
17:31 Hugh out to LVEA/HAM1 area to investigate some audible HEPI noise that Robert reported.
17:35 Lockloss
18:40 Kyle out to Y-2-8
19:48 Kyle back from Y-2-8
21:47 Chris driving to MX to work in a fan room.
22:48 Kyle out of EY mech room and going to Y-2-8
23:07 kyle driving back to corner to get keys.
23:23 Kyle driving back down to Y-2-8.