Reports until 18:01, Monday 25 October 2010
H2 INS
patrick.thomas@LIGO.ORG - posted 18:01, Monday 25 October 2010 (242)
Ops Day Summary
Richard and Filiberto started pulling the H2 electronics from the LVEA.

H0:FMC-MX_CY_H2O_PUMPSTAT is failed. See Ski's elog
Sno Valley came to look at the part numbers for the pump.

Keita and Dani started pulling optics from ISCT7.

Rick rigged up a HEPA filter near HAM12 to pull in the dust from the scouring.
Corey and Eric finished the prepping work for the HAM12 pier anchor bolts.

Kyle closed GV1, GV2, GV10 & GV11, started venting the vertex and HAM6.

Gerardo removed the H2-ETMY transmission monitor.

Jodi and Ski prepped for the BSC1 vent and worked on the clean room at mid Y.

Apollo cleaned at Y end.

Cyrus turned tidal off.

John Zweizig started migrating the DMT viewers to the advanced ligo configuration.

Dave removed the disconnect channels from the EDCU.

Reboldt worked at the LSB.