Ops Day Summary: 16:00-23:59UTC, 08:00-16:00PT
State of H1: down since 18:15UTC, high useism, winds increasing, not able to get to DRMI
Outgoing Operator: Jeff
Incoming Operator: TJ
Shift Details:
-
H1:
-
lost lock at 18:15UTC, coincident with a spike in the 0.003-0.1um/s seismic
-
needed an Initail Alignment
-
woth little hope of locking, we took some time for commissioning
-
Jim took some measurements with alternative SEI filters in the Find IR state
-
MICH Dark did not work today
-
Jim needed PRMI or DRMI for his next measurements, and neither locked
-
alignment has been very dynamic, meaning every time H1 drops from trying to lock DRMI, the arms in green need to have the ETMs adjusted to get back to a 0-0 mode, but no WFS troubles, I think just a lot of ground motion
-
VerbalAlarms are broken - TJ is here and looking into it
Site:
-
Gerardo to MY to manually fill CP3, will be ongoing
-
CP3 on VAC overview is reading zero, but it is being watched closely
-
deliveries at OSB, LSB, and Staging Building
-
useism is about 1um/s in the CS
-
winds have increased and are now c-25mph across the site
-
HVAC work today increased the elements for heating