jeffrey.bartlett@LIGO.ORG - posted 16:01, Saturday 02 January 2016 (24644)
Ops Day Shift Summary
Activity Log: All Times in UTC (PT)

00:00 (16:00) Take over from TJ
21:20 (13:20) SDF difference on EY ECAT PLC2 – Called Sheila (see aLOG #24640)
21:35 (13:35) Kyle – On site to over fill Mid-Y CP3
22:20 (14:20) Kyle – Leaving site
22:29 (14:29) GRB Alert – In 1 hour hold. LLO down. 
23:30 (15:30) Stand down from GRB alert hold
00:00 (16:00) Turn over to Travis


  
End of Shift Summary:

Title:  01/02/2015, Day Shift 16:00 – 00:00 (08:00 – 16:00) All times in UTC (PT)

Support:  Vinny, Sheila,  
 
Incoming Operator: Travis

Shift Detail Summary:   Fiber Wrong Polarization was getting very close to limit of 40. Trend shows swings over time. This will not affect the IFO while in lock, but could make relocking difficult if still high. At shift end, this had dropped to around 32. 

    OK shift – In Observing mode for full shift. Environmental conditions were good for the shift. Range was in the high 70s to low 80Mpc for the shift. There were several (15 plus) ETM-Y saturations, which knocked down the range a bit.

   It has stopped snowing. Since it was a dry light snow, there was not much accumulation. Still very cold at the site – around 18F.