bubba.gateley@LIGO.ORG - posted 15:42, Tuesday 05 January 2016 (24712)
MID Y PIPE RELOCATION
Pipes under the beam tube have been rerouted to allow access under the tube with a pallet jack. This relocation required a brief shutdown of the instrument air which caused some alarms. The control room was notified in advance of the shutdown. The instrument air is back to normal operation.