Reports until 15:42, Thursday 22 March 2012
H1 AOS
jodi.fauver@LIGO.ORG - posted 15:42, Thursday 22 March 2012 (2472)
HAM3 ICC
Support tubes were picked clean of fibers and bellows were vacuumed. Dust barriers were installed and then support tube protection was installed. Brushing began and all but three sections of the floor were completed. Four drills were used.