travis.sadecki@LIGO.ORG - posted 16:01, Wednesday 06 January 2016 (24731)
OPS Day Shift Summary

Title: 1/6 Shift 16:00-24:00 UTC (8:00-16:00 PST).  All times in UTC.

State of H1: Locking/Commissioning

Shift Summary: We have been struggling to acquire lock all day due to issues with ASC loops.  Commissioners are working on it and hopefully we are nearing success.  Microseism is trending up and is currently at 0.6 um/s.  Wind is calm.

Incoming operator: Cheryl

Activity log:

19:00 Kyle and Gerardo to Mid Y

19:54 Kyle and Gerardo back

23:34 Kyle to Mid Y

23:54 Kyle back