H2 INS
jodi.fauver@LIGO.ORG - posted 09:17, Wednesday 28 March 2012 (2492)
Prep for BSC6 Cartridge Install
Staging work continued yesterday. Kyle vented the volume on Monday, so the Apollo crew broke bolts on the dome and the doors and installed a soft roof. The west (end) door was removed using the large engine hoist and then laid down on the north side of the beamtube. A soft cover was placed on the opening. One leg was removed from the E-module so that the engine hoist could be moved to the north side of the chamber (A very tight fit!). Once the hoist was in correct position, the leg was restored to its rightful place. Two chamber-side carts, BSC flooring, vertical dispenser of foil and CPStat were hauled from the corner to the end.