H2 INS
jodi.fauver@LIGO.ORG - posted 14:21, Friday 30 March 2012 (2512)
Prep for BSC6 Cartridge Install
The following activities took place yesterday in preparation for cartridge install:
-BSC flooring hardware was installed
-Hand rails were removed from the work platforms
-Chamber cleanroom was lowered
-A manlift was craned across the beamtube for Dale's use
-Upper level garbing/staging cleanroom was moved into place