Reports until 09:19, Monday 01 February 2016
H1 General
jeffrey.bartlett@LIGO.ORG - posted 09:19, Monday 01 February 2016 (25284)
08:30 Meeting Minutes
SEI – OK
SUS – Charge measurements
CDS – OK
FMP – Final carpet installation on Wednesday. Ongoing shimming the LVEA main crane. 
VAC – OK
PSL – High Power checkout work 
TCS – Guardian updates, Check out and commissioning. Prep work to turn on TCS-Y laser
General commissioning work continues. Commissioning meeting at 09:00 in control room
Outreach – Dale will conduct two tours through the control room around noon 

Outstanding work permits were reviewed. 
Reviewed planned work for Tuesday maintenance