Reports until 07:31, Wednesday 04 April 2012
H1 FMP
jodi.fauver@LIGO.ORG - posted 07:31, Wednesday 04 April 2012 (2535)
HAM2 ICC
This report is for 03 April 2012. Viton rim was installed on the second dust barrier. The condition of the chamber was documented and then the support tubes were inspected. Then, the tubes were picked and vacuumed. Support tube/bellows protection and dust barriers were installed. The chamber is ready for brushing.