Subsystem Status
-
SEI: Upgraded ISI Guardian stuff, but HAM2/3 still need to be manually addressed by Operator (toggle GS13 gains via scripts) [Hugh]
-
SUS: Noise in a PR optic narrowed down (Evan), and will be investigated [Richard]
-
PSL: Nothing [Peter]
-
Vac/Facility: beamtube cleaning/sealing, need to fly genie over arms & viewport work (requiring GV soft close) [Bubba/John]
Reviewed work permits.
Items for Tues Maintenance
-
Dust Monitor screens & vacuum work
-
PSL ISS modification (needs IMC for 2-3hrs), DAQ restart (Kiwamu)
-
End Station ESD driver work, re-terminating cables (Fil)
-
SUS Noise Evan found investigation (Richard)
-
End Station charge measurement
-
Kyle high voltage cabling continues
-
Boom lift taken to an end station (Bubba)
-
Control Stations Network at LSB TODAY (Bubba)
-
2pm CDS Meeting to happen
-
Clearing out racks in Mechanical Room, so can clear out off-site warehouse
On the Alarm Handler, there were alarms for: