H1 FMP
jodi.fauver@LIGO.ORG - posted 19:06, Wednesday 04 April 2012 (2544)
HAM2 ICC
Mechanical brushing started this morning and about half of the chamber was brushed by ~10am. The remainder of the chamber was finished shortly after lunch. Hand brushing the details was about 3/4 complete by the time the crew came out early for safety meeting. The drills did not do well today: 7+ for this chamber with 3-4 DOA (meaning they would not even turn).