H1 FMP
jodi.fauver@LIGO.ORG - posted 15:58, Thursday 05 April 2012 (2548)
HAM2 ICC
The balance of the hand brushing, first vacuum and wipe down were completed. That leaves second vacuum and close-out for tomorrow.
*Note-It seems that the doors on HAM1 WERE NOT removed at the same time as the doors on HAM2 despite what the work permit says!The most likely scenario is that HAM1 doors will come off when the HAM2 doors go back on.