patrick.thomas@LIGO.ORG - posted 16:21, Monday 22 February 2016 (25665)
Ops Day Summary
15:20 UTC Chris S. starting beam tube tunnel sealing (first 150 yards of X arm)
16:19 UTC Elli, Cao to Y arm TCS table to check beam
16:39 UTC Elli and Cao back
17:21 UTC Ed and I done transitioning LVEA to laser safe, Bubba and John starting crane shimming
17:45 UTC Richard to H1 PSL enclosure to check door lock
17:50 UTC Kiwamu, Elli and Cao to LVEA to turn on Y arm CO2 laser
17:51 UTC Richard back
17:57 UTC Kiwamu, Elli and Cao back
18:07 UTC Karen and Christina opening OSB receiving door to bring in 51 lb package
19:01 UTC John and Bubba done for the day
19:26 UTC Dave rebooting hardware injection machine (WP 5740)
19:53 UTC Dave done
21:20 UTC ASCIMC model restarted
21:22 UTC LSC model restarted
21:24 UTC DAQ restart
21:32 UTC Kiwamu transitioning to laser hazard
21:39 UTC Kiwamu done transitioning to laser hazard, Elli and Cao to ISCT6
22:03 UTC Vinny and Brynley to end Y, opening middle rollup door to move temporary magnetometer

- beam tube tunnel sealing (Chris S.)
- crane work (John, Bubba)
- TCS work (Elli, Cao)
- ASCIMC and LSC model changes (Sheila)
- PEM work (Vinny and Brynley)
- tconvert fix (Dave)