sheila.dwyer@LIGO.ORG - posted 02:25, Saturday 05 March 2016 (25890)
Daytime RF centering work

Jenne, Hang, Sheila, Rob,

durring the day today we worked on RF centering a bit more.  No real breakthroughs, but there are a few things to note:

The lock point of the MICH loop is not necessarily good when we are locked with RF centering.  The problem could be that we have the SRC uncontrolled when we are using RF centering, and currently the phasing of AS36 is set to maximize BS in Q, not to minimize SRM in Q which is what we probably want.  Or it could be that we need to check the gain matching on the quadrants for the 90 MHz centering.