Displaying report 1-1 of 1.
Reports until 14:13, Thursday 12 April 2012
H1 INS
jodi.fauver@LIGO.ORG - posted 14:13, Thursday 12 April 2012 (2603)
BSC3-2-1 De-install
After a bit of planning, a work permit was generated for the H1 BSC de-install. The tentative plan is to enter BSC3 through the east door and remove optics from BSC3-2-1 and then strip the guts from BSC3 so that we can chamber clean it. The work permit includes staging cleanrooms, etc. and door/dome removal.
Displaying report 1-1 of 1.