TITLE: 03/15 day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC STATE of H1: Planned Engineering INCOMING OPERATOR: Jeff SHIFT SUMMARY:'Maintenance LOG: 14:15 Chris S; X-Arm beam tube sealing; 300 yards from end station. (morning work) 15:00 Grouting in LVEA 15:48 Hugh out to LVEA work around HAM2. Jim handling ISI damping. 16:30 Fil into LVEA to do WP5778 16:27 Bubba going to MX and EX with Cintas people. 16:45 NORCO on site with LN2 load for EX 17:00 Fil called from LVEA. Key Lock is intslled on TCS Y and by Kiwamu's instruction, ENABLED. FIl heading to do the same for TCS X. 17:15 Water Delivery 17:29 Second LN2 truck on site 17:43 Fil back from LVEA. TCS Y Key Lock done. Heading back out to execute WP5735 18:19 Joe, Sheila and Hang out to LVEA 18:40 Joe out of the LVEA 19:05 Truck here to pick up rental equipment 19:00 Fil out of LVEA for lunch 20:53 Carlos to reboot all workstations at end stations 21:18 Joe back into the LVEA 21:30 Fil and Manny out of LVEA 21:40 Joe out 21:55 Jeff to both end stations 22:18 Gerardo to MY/CP3 for manual fill 22:24 Fil out to LVEA to retrieve cables 22:30 Bubba out of fan room headed to EX 22:35 Gerardo is back from MY/CP3