Grouting of the remainder of the HEPI piers, transmitter and receiver pylons in the LVEA began on Monday morning by Reiboldt and Associates. The grouting has consumed more product than was originally expected and we have used up all that we had. I have ordered more grout and that should be onsite today, meanwhile, the grout crew will be out today. Progress to date includes, all of the HEPI piers on HAM 5 & 6, the large carbon fiber leaner on the south side of HAM 4, and the large stainless steel leaner pylon on X-Arm. Remaining items to grout in the LVEA include, 5 of the small transmitter pylons, and 1 each of the large carbon fiber and stainless steel leaner pylon. The plan is to finish these items in the LVEA tomorrow and move to the End stations afterwards.