Activity Log: All Times in UTC (PT) 15:00 (08:00) – Start preparing the IFO for relocking. 17:00 (10:00) HFD will be doing prescribed burning to the NW of the site 17:01 (10:01) Bubba – checking on tumbleweed accumulation in desert between the arms 17:17 (10:17) Richard, Jenne, Hang – Going into LEVA to look at camera pointing 17:24 (10:24) Kiwamu & Patrick – Going into the CER to check the TCS-X Beckhoff 17:28 (10:28) Christina & Karen – Cleaning up at End-Y after grouting work 17:30 (10:30) Stefan – Going into LVEA to work on camera pointing 17:45 (10:45) Reboot Video4 to fix frozen displays 18:04 (11:04) Bubba – Back from the desert 18:05 (11:05) Grout work is finished at End-Y and in the LVEA 18:15 (11:15) Rick – Taking tour through LVEA 18:20 (11:20) Sheila & Jeff – Transition LVEA to laser hazard 18:30 (11:30) Rick – Taking tour to roof top observation deck 18:33 (11:33) Nutsinee – Recovering parts from the LVEA 18:55 (11:55) Rick – Off the LVEA roof 19:00 (12:00) Hugh – Going into the LVEA 20:40 (13:40) Travis – Going into Optics Lab 20:45 (13:45) Sheila – Going into LVEA to replace VP covers 20:50 (13:50) Sheila – Out of LVEA 20:52 (13:52) Travis – Out of the Optics Lab 21:08 (14:08) Filiberto & Tara – Going to both end stations electronics rooms 22:28 (15:28) Dave & Jim – Going to the End-Y CER 22:32 (15:32) Kyle – Going to do CP-3 fill 22:51 (15:51) Kyle – Back from Y-Arm 23:00 (16:00) Turn over to Ed End of Shift Summary: Title: 03/21/2016, Day Shift 15:00 – 23:00 (08:00 – 16:00) All times in UTC (PT) Support: Commissioning crew Incoming Operator: Ed Shift Detail Summary: Commissioning team has been work on relocking the IFO today. Many problems have been fixed. Wind is coming up and is currently between a moderate and strong breeze (15 – 28 mph); there have been gusts in the mid 30 mph. Seismic activity is up a bit at the end stations. Microseism is also a little high but still within the bands.