Reports until 18:40, Tuesday 22 March 2016
H1 ISC
stefan.ballmer@LIGO.ORG - posted 18:40, Tuesday 22 March 2016 - last comment - 21:51, Tuesday 22 March 2016(26201)
Moved InAir 36/45MHz WFS from ISCT6 to ISCT1

Corey, Daniel, Stefan

We moved one of the two AS56/45 WFS from the AS port in-air table (ISCT6) to the REFL port in-air table (ISCT1). (Serial number S1300512)

The WFS was connected to the RF cables for the REFLAIR B WFS, and powered by the third slot on the WFS interface chassis.

 

One thing to note (again) is that those 5-channel RF connetors are impossible to plug in - in fact the only way to guarantee that all connecions are good is to remove both the connector backshell and the WFS box cover, and idividually checking that every channel pin and shield makes a good contact. Corey has some pictures of this.

 

Also, we quickly wanted to check the RF transfer functions from test in to each channel, but they looked broken. The chain definitely needs to be checked out again.

Comments related to this report
corey.gray@LIGO.ORG - 20:39, Tuesday 22 March 2016 (26205)

As Stefan notes, the "connectors" for the WFS were a bear to work with.  Since the pins would move, and you never knew if the connector was really connected, Stefan removed the covers to the connectors, and also removed the back panel of the WFS to make sure the connector is connected.  He did this on both. 

To remove the connectors, one will need to remove the connector covers, and then disconnect the connectors (not ideal, we know).

Attached are photos of the connectors connected (with WFS panel removed and connector covers removed).

Images attached to this comment
daniel.sigg@LIGO.ORG - 21:51, Tuesday 22 March 2016 (26206)

MCL controller:

  • Feedthrough panel installed
  • Rack mount posts installed
  • MCL controller set on top of table
  • DB9 cables connected to feedthrough
  • Missing: rack mount brackets, power cable & BNC cables to driver

PZT mirror:

  • Missing: MCL mirror mount, base & mirror

WFS:

  • WFS head cabled and power up
  • demod chassis powered up & LO connected
  • Missing: move REFLAIR_B RF cables to POP_X patch panel
  • Missing: signal chain check

Model/DAQ:

  • All cables connected
  • Model updated
  • Missing: signal chain check

ISCT1:

  • 36MHz WFS is placed
  • Missing: PZT steering mirror setup & lens
  • Missing: modifications to the POP beam path