Reports until 18:12, Wednesday 23 March 2016
H1 SEI (CDS, SEI)
krishna.venkateswara@LIGO.ORG - posted 18:12, Wednesday 23 March 2016 (26224)
BRS-2 Installation DAY 0: Instrument delivered

Krishna, Michael,

We left Seattle at 10 AM and reached LHO at 2ish PM. Hugh helped us unload the BRS-2 vacuum can and other parts into the 'loading bay' at the Y-End-station. Tomorrow morning, we will clean them and move them in and begin assembly, which is expected to take 2-3 days and commissioing/debugging may take a week. We will try to complete activities in the VEA by mid-day to minimize impact on commissioining.