Reports until 11:40, Friday 01 April 2016
H1 SEI (ISC, SEI, SYS, VE)
vernon.sandberg@LIGO.ORG - posted 11:40, Friday 01 April 2016 - last comment - 08:32, Monday 04 April 2016(26389)
HAM6 Vent Plan for the Week of April 4, 2016

B. Weaver, H. Radkins, V. Sandberg

 

LHO WHAM6 Vent Plan for 2016 April 04 - 08

DCC Document: E1600092, “HAM6 - ISI Damper Install”

https://dcc.ligo.org/LIGO-E1600092

 

APPROVED work to be done in order of importance:

Install HAM ISI Dampers assemblies (Jim W., Nutsinee K.). 

Retune Tuned Mass Dampers (TMDs).

 

DCC Vent Documents referenced in this plan:

a)   D1500469 Drawing documents for ham blade dampers

b)   D1600085  Drawing documents for GS13 dampers

c)   D1500200  Drawing documents for flexure dampers

d)   D0900703  Drawing documents for Tuned Mass Dampers (TMDs)

e)   E1100963  Retuning the TMDs

f)   T1500580 HAM ISI Damping Study - Mittleman

g)   G1500880  Damping Tests on Flexture Demo - Lantz

 

SCHEDULE

MON  April 4, 2016  (possibly prior if time allowed)

1)    Transition to LASER SAFE

2)    Turn cleanrooms on around HAM6

3)    Mark and move ISCT6 out of the way to facilitate door removal

4)    Clean area, door flange, and cleanrooms

5)    Stage supplies and equipment

a)     Contamination control kit

b)    B&K hammer setup and computer

c)     Various ISI damper assemblies

d)    ISI tool kit, TMD table setup

e)     ISI parts as per E1600084

f)     Septum viewport cover D1200448

6)    Confirm dust monitor is working

7)    Lock HEPI

8)    Confirm purge air is on at HAM6

9)    Vent HAM6

 

TUES  April 5th, 2015

10)     Remove ALL 3 CHAMBER DOORS – Review and follow M1100039 “ Hanford checklist – HAM Door Removal”

11)     Entry chamber checklist items: Pick up floor CC wafers.  Take particle counter measurements and record:

12) SEI Lock ISI 

13) Entry chamber checklist items: Pick up table top CC wafers. 

14)Install Septum Window Cover

15) Evaluate, mark and Move Beam Diverter ONLY IF ABSOLUTELY NEEDED for ISI work.  IF CABLES of Beam Diverter get removed, a test of the Beam Diverter function will need to be made before closeout.

16)     Start ISI damper install work. 

a) ISI Wall units need to be moved for this work. 

Note, DO NOT REMOVE ANY TABLE TOP OPTICS.  Confer with Keita before hand if this is needed.

b) Remove Tuned Mass Dampers (TMDs)

c) Install new spring damper assemblies

d) Measure new spring modes using the B&K System

e) Retune TMDs with new info

f) Reinstall TMDs

 

WED  April 6th, 2016

17) Continue ISI damper install work.

18) Take particle measurements and record:

 

THUR  April 7th, 2016

19)  Finish ISI damper install work

20)  Check Beam Diverter functionality

21)  Quick check of ISI Balance and clean TF

22)  Remove Septum Window Cover

23)  Chamber closeout – perform applicable exit checklist tasks E1201035.

24)  Take particle count measurements and record:

25)  Replace 1 HAM6 door if possible

 

FRI,  April 8th, 2016

26)  Replace remaining HAM6 Doors

27)  Begin pump down

              28)  Reset ISCT6

 

Comments related to this report
hugh.radkins@LIGO.ORG - 08:32, Monday 04 April 2016 (26416)

See D1201388-v4 for as-built of the Optical Table top payload, which may need to be removed temporarily.