Reports until 11:26, Monday 04 April 2016
H1 General
jeffrey.bartlett@LIGO.ORG - posted 11:26, Monday 04 April 2016 (26421)
Prep for HAM6 Vent
   Cleanroom over HAM5 & HAM6 has been patched up and is powered up. A first cleaning was done this morning. Clean crew (give them a big thanks for the phenomenal job of maintaining cleanliness in the LVEA and at the Ends) gave the floor an extra scrub. Initial dust counts do not look too bad considering the activities this morning around HAM6.

   Staged two small cleanrooms on the south wall ahead of the doors coming off. Several work tables have also been staged.

   Will do a second cleaning tomorrow morning before the doors come off.