Day Shift Summary: Title: 04/08/2016, Day Shift 15:00 – 23:00 (08:00 – 16:00) All times in UTC (PT) State of H1: IFO unlocked. HAM6 vented for ISI upgrade. Commissioning: Outgoing Operator: N/A Activity Log: All Times in UTC (PT) 15:00 (08:00) – Start of shift 15:45 (08:45) Jeff k., Jim, Corey – Working at HAM6 15:55 (08:55) Peter, Jason, Ed – Working in the PSL 16:15 (09:15) Patrick – Working on the End-X vacuum computer for new gauge install 16:30 (09:30) Patrick – Restarted the End-X vacuum computer 16:35 (09:35) Jeff K., & Evan – Confirmed the fast shutter is operating & out of LVEA 16:40 (09:40) Filiberto & Manny – Going to End-X to recover tools 16:42 (09:42) Jim & Corey – Finished at HAM6 – Out of LVEA 17:37 (10:37) Patrick – Restarted the End-X vacuum computer 18:00 (11:00) Kyle, Chandra, Gerardo, Jeff B. – Reinstall north and south HAM6 doors 22:00 (15:00) Kyle, Chandra, Gerardo, Jeff B. – Out of the LVEA 22:40 (15:40) Kyle, Chandra – Starting pumping and leak checks on HAM6 End of Shift Summary: Title: 04/08/2016, Day Shift 15:00 – 23:00 (08:00 – 16:00) All times in UTC (PT) Support: Incoming Operator: Shift Detail Summary: SEI upgrades are finished. TFs for HAM6 look good. Reinstalled the north and south doors on HAM6. Vacuum group is pumping down and doing leak checks.