Displaying report 1-1 of 1.
Reports until 17:50, Friday 08 April 2016
LHO VE
chandra.romel@LIGO.ORG - posted 17:50, Friday 08 April 2016 (26512)
HAM6 east door leak
Not pumping HAM6 chamber over the weekend because we found a leak on east door. We will need to pull off door to repair o-ring leak on Monday if leak rate is too big. Quantifying leak rate early Monday morning, after leak checker has had time to run and stabilize. North and South doors passed leak check test. 
Displaying report 1-1 of 1.