MONDAY MEETING:
General Announcement: It's always best to provide data in alogs. If you have a long entry, perhaps the bulk of this should be entered as a document in the DCC. (Vern)
SEI: All vibration absorbers installed, and B&K measurements look good! ISC (i.e. Evan) tested ISC items such as shutters. (Jim)
PSL: Summary given for work from last week and HPO work continues this week. (Jason)
VAC: 5pm fri & doors on. GV5&7 opening hopefully this afternoon (Chandra)
Miscellaneous:
-
Japanese film crew setting up camera along arm(s) for time lapse video (Keita)
-
Shaker moved during HAM6 Door install (& returned) (Kyle)
-
Went over Work Permits
-
Reminded everyone about posting work permits for Maintenance Tuesday
COMMISSIONING MEETING
-
High freq HAM6 measurments still needed (Robert)
-
PSL: survey tweaking; hard to know how long will take to complete HPO work (currently have 30W going into PMC & 27W coming out). More tweaking today and possibly tomorrow during Maintenance.
-
ISS feedback work tomorrow for Mainteance (Kiwamu)
-
Engaging ETM oplevs (in addition to ITM oplevs) (Kiwamu)
-
Rotation stages behaving better, more measurements when we have beam (Vern)
-
BRS are waiting for wind. ETMx code changes this week (Krishna, Michael)
-
Commissioning This Week: Starting probably wednesday?
-
Need IMC locked to do alignment on ISCT6.
-
POP_X work,
-
TCS?(high power, kind of good starting point, fine tuning needed),
-
ASC? (squashing power isolation),
-
Cavity pole....
-
General locking