Title: 04/13/2016, Day Shift 15:00 – 23:00 (08:00 – 16:00) All times in UTC (PT) State of H1: IFO unlocked. HAM6 being pumped. Work on PSL is ongoing Commissioning: Outgoing Operator: N/A Activity Log: All Times in UTC (PT) 15:00 (08:00) – Start of shift 15:44 (08:44) Christina & Karen – Going into LVEA for cleaning 15:52 (08:52) Kyle – Going into LVEA to move vacuum pump from north side of HAM6 15:57 (08:57) Keita – Going to ISCT1 to do fit checking 16:09 (09:09) Peter – Going into LVEA to make measurements 16:14 (09:14) Gerardo – Going to Y-End to recover Pump cart 16:28 (09:28) Peter – Out of the LVEA 16:29 (09:29) Chris – Beam sealing on the X-Arm near the corner station 16:42 (09:42) Filiberto – Taking job shadows into CER 16:50 (09:50) Filiberto & Job shadows – Going to Mid-Y to prep for vacuum system changes 16:58 (09:58) Kyle – Out of the LVEA 17:05 (10:05) Gerardo – Back from End-Y 17:09 (10:09) Kyle & Gerardo – In LVEA craning the pump cart over the beam tube 17:15 (10:15) Peter & Jason – Going into the PSL enclosure 18:10 (11:10) Dale – Taking job shadows on LVEA tour 18:14 (11:14) John – Going to both mid stations to check property tags 18:38 (11:38) Dale – Out of LVEA 18:50 (11:50) Filiberto – Back from Mid-Y 18:52 (11:52) Filiberto – Going to Mid-X 19:06 (12:05) Dave & Jim – DAQ restart Taking down FW0 for several hours to move disks Taking down NDS0 – May cause Guardian to crash 19:15 (12:15) Filiberto – Back from Mid-X 19:19 (12:19) Kyle – Out of LVEA 19:29 (12:29) Jason & Peter – Finished in the PSL enclosure 19:31 (12:31) Jim – Restarting H0EPIC2 to fix a pegged CPU 19:49 (12:49) Jeff K. & Evan – Going to End-X to hunt for noise 20:51 (13:51) Krishna – Going to End-X for BRS code changes 21:40 (14:40) Filiberto – In Beer Garden working on Newtonian array 21:46 (14:46) Peter & Jason – In LVEA around PSL racks 21:55 (14:55) Chandra & John – In LVEA at GV3 22:15 (15:15) Keita – Finished moving the ISCT6 table back into place at HAM6 22:18 (15:18) John & Chandra – Out of the LVEA 22:26 (15:26) Krishna – Back from End-X 22:58 (16:58) Jeff K. & Evan – Back from End-X End of Shift Summary: Title: 04/13/2016, Day Shift 15:00 – 23:00 (08:00 – 16:00) All times in UTC (PT) Support: Incoming Operator: Nutsinee Shift Detail Summary: Chamber pump down continues at HAM6. The PSL team is working on a power stabilization problem located outside the PSL enclosure. Various other groups are taking advantage of the IFO being unlocked to address problems, upgrades, and fixes.