H1 General
edmond.merilh@LIGO.ORG - posted 06:23, Friday 15 April 2016 (26602)
Shift Summary - Day
TITLE: 04/14 Day Shift: 15:00-23:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
    Wind: 24mph Gusts, 18mph 5min avg
    Primary useism: 0.32 μm/s
    Secondary useism: 0.66 μm/s 
QUICK SUMMARY: 

15:00 Observed activitiy in the PSL enclosure. - Peter

15:00 Snow Valley on site - headed down X arm.

15:10 John to EX to meet Snow Valley

15:15 Jeff B into LVEA

15:20 Krishna and Mike to EY 

15:22 Ops Dailty Checkk List tasks performed: Vidoe0 and Video5 FOM computers needed restart.

15:29 Jeff out of LVEA and goin to both ends

15:53 Jason into PSL

16:08 Gerardo to Y end to check on ION pump

16:18 Jeff Back

16:27 John back

16:39 Gerardo back

16:45 John to MY

17:00 Richard ou to LVEA for scope inventory

17:12 Krishna and Mike back

17:17 Krishna and Mike to EX

20:21 Jeff into PSL to connect dust meter

19:59 Jeff back

17:23 Richard out and heading to the out buildings

17:44 DAQ restart

18:34 Richard back

19:35 Jenne into the LVEA with two guests

19:47 Jeff into LVEA

19:54 Tour group into control room

 

 

 