15:00 Observed activitiy in the PSL enclosure. - Peter
15:00 Snow Valley on site - headed down X arm.
15:10 John to EX to meet Snow Valley
15:15 Jeff B into LVEA
15:20 Krishna and Mike to EY
15:22 Ops Dailty Checkk List tasks performed: Vidoe0 and Video5 FOM computers needed restart.
15:29 Jeff out of LVEA and goin to both ends
15:53 Jason into PSL
16:08 Gerardo to Y end to check on ION pump
16:18 Jeff Back
16:27 John back
16:39 Gerardo back
16:45 John to MY
17:00 Richard ou to LVEA for scope inventory
17:12 Krishna and Mike back
17:17 Krishna and Mike to EX
20:21 Jeff into PSL to connect dust meter
19:59 Jeff back
17:23 Richard out and heading to the out buildings
17:44 DAQ restart
18:34 Richard back
19:35 Jenne into the LVEA with two guests
19:47 Jeff into LVEA
19:54 Tour group into control room
note to self: press 'Post to Logbook' :)