TITLE: 04/20 Day Shift: 15:00-23:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: Nutsinee
SHIFT SUMMARY: In the morning the commissioners started some green alignment and then the PSL blew a water hose. PSL crew wants to leave it to dry overnight. Other various maintenance tasks throughout the day.
LOG:
-
15:08 - Christina opening rollup door.
-
17:09 - Jeff B to Diode room for dust monitor work.
-
17:22 - Jason, Peter into PSL enlcosure to look for water leak.
-
17:30 - Jeff B to LVEA recovering electronics.
-
17:43 - Travis to LVEA to gather parts to send to LLO.
-
17:44 - Jeff B out.
-
17:50 - Travis out.
-
18:09 - Ed M to LVEA placing power supply in closet.
-
18:20 - Christina, Karen to MX.
-
18:50 - Jason, Peter out. Hose burst, waiting for the rest of the area to dry and lunch.
-
19:05 Ed out for lunch
-
19:37 - Travis to LVEA finding more parts.
-
19:46 - Travis out of LVEA, headed to optics lab.
-
19:56 - Travis out.
-
20:11 - Christina, Karen back.
-
20:15 - Ed M to LVEA to continue work.
-
20:21 - Kyle to MX to look at gauge.
-
20:25 - Jason, Peter to PSL enclosure.
-
20:45 - Chris S to EX then EY.
-
21:00 - DAQ restart.
-
21:02 - Ed M out.
-
21:08 - Dave restarted H1SUSETMXPI
-
21:17 - Ed M Back out to LVEA.
-
21:28 - Jason, Peter out. Laser will be kept off overnight to dry.
-
21:38 - Kyle back.
-
22:00 - Kyle to MY to fill CP3
-
22:24 - Kyle back.
-
22:44 - Ed M out.