kyle.ryan@LIGO.ORG - posted 17:39, Friday 29 April 2016 - last comment - 11:59, Saturday 30 April 2016(26892)
LHO VBOC repair/upgrade on schedule
Kyle, Joe D.  

We removed the dying and obsolete iLIGO SRS RGA from VBOC and installed the latest/greatest aLIGO Pfeiffer Prisma Plus yesterday -> Today we took it for a test drive in both Faraday and Multiplier modes and it looks great.  This should have been done a long time ago.  The data finally looks normal!  We are baking this new RGA over the weekend -> VBOC should be available for Bake Loads by mid week.  
i
We are planning to rebuild VBOD's SRS RGA in the VPW and are considering baking it "nude" to expedite its clean-up.  We will also be replacing the RGA-tree isolation valve so VBOD will be out all of next week and perhaps longer.  