jeffrey.bartlett@LIGO.ORG - posted 16:00, Monday 02 May 2016 (26934)
New Dust Monitors in the PSL
   Completed the installation of the new dust monitors in the PSL enclosure this afternoon. All the new dust monitors for LHO are operational. The alarm levels have been set, so any alarms received at the operators station should be investigated as a true event. 

   Last task is to clean up the supporting documentation.   