Displaying report 1-1 of 1.
Reports until 17:23, Tuesday 03 May 2016
LHO VE
kyle.ryan@LIGO.ORG - posted 17:23, Tuesday 03 May 2016 (26973)
~1200 hrs. local -> bake of Vertex RGA started
Kyle 

Multiple hiccups delayed the actual start of the bake and, as such, this exercise will now drag into Friday -> I am utilizing a second isolation valve via adding, in series, the turbo+gauge portion of a donor pump cart.  I modified the wiring so that this redundant isolation valve closes on a fore line pressure set point. The nominal fore line isolation valve closes only upon the loss of AC to the scroll pump motor.  
Displaying report 1-1 of 1.