Transition Summary: Title: 05/09/2016, Day Shift 15:00 – 23:00 (08:00 – 16:00) All times in UTC (PT) State of H1: IFO unlocked. Work on PSL is ongoing Commissioning: Outgoing Operator: N/A Activity Log: All Times in UTC (PT) 15:00 (08:00) – Start of shift 16:22 (09:22) Peter – Going into PSL to pull inner loop photodiode box (WP #5872) 16:25 (09:25) Kyle – In the LVEA working on RGA 16:40 (09:40) Jason – Going into the H1 PSL enclosure 16:45 (09:45) Kyle – Craning leak detector over the X-Beam manifold 16:57 (09:57) Kyle – Finished craning in LVEA 17:00 (10:00) Bubba – Filling the water tank in the End-Y compressor room 17:20 (10:20) Open gate for people coming to see Ed for Mercury transit 18:00 (11:00) Bubba – Back from End-Y 19:50 (12:50) Jason & Peter – Out of PSL 20:00 (13:00) Dale – High school tour of control room 20:25 (13:25) Corey – Going into Optics Lab 20:45 (13:45) Dave – DAQ restart 20:50 (13:50) Sheila & Jeff – Reset ALS fiber polarization for X and Y 21:45 (14:45) Kyle – Going into the LVEA to check RGA temperatures 22:01 (15:01) Kyle – Out of the LVEA 22:10 (15:10) Peter – Going into the H1 PSL enclosure 22:38 (15:38) Kyle – Going into LVEA to check RGA temperatures 22:45 (15:45) Jason – Going into the H1 PSL enclosure End of Shift Summary: Title: 05/09/2016, Day Shift 15:00 – 23:00 (08:00 – 16:00) All times in UTC (PT) Support: Incoming Operator: Cheryl Shift Detail Summary: Work continues on the PSL and vacuum system. Other groups taking advantage of this time to make updates and upgrades.