Transition Summary: Title: 05/10/2016, Day Shift 15:00 – 23:00 (08:00 – 16:00) All times in UTC (PT) State of H1: IFO unlocked. Work on PSL is ongoing. Tuesday Maintenance day Commissioning: Outgoing Operator: N/A Activity Log: All Times in UTC (PT) 14:00 (06:00) Peter – In the H1 PSL enclosure 14:30 (07:30) Jeff – Replace network cable to PSL dust monitor #102 15:00 (08:00) Start of Tuesday maintenance day 15:00 (08:00) Christina & Karen – Cleaning in the LVEA 15:14 (08:14) Sprague – on site to remove pest control boxes 15:30 (08:30) Hugh – Restarting HAM models (WP #5874) 15:48 (08:48) Filiberto, Leslie, & Manny – Going to pull cables for the access system 15:49 (08:49) Hugh – Finished with model restarts 15:54 (08:54) N2 delivery at both end stations 16:00 (09:00) Patrick – Update Beckhoff code for vacuum controls computer (WP #5875) 16:04 (09:04) Kyle – Going to both end stations VEAs. 16:10 (09:10) Jim B – Restarting H0EPICS to apply security patch. 16:10 (09:10) Bubba – Replacing faulty check valve air comp at Mid-X (WP #5876) 16:15 09:15) Peter – Out of the H1 PSL enclosure 16:17 (09:17) Filiberto – Power off Vac rack LX, & LY to check grounds 16:35 (09:35) Christina & Karen – Cleaning at End-X 16:35 (09:35) Chandra – Going to Mid-X to work on CP4 16:36 (09:36) Kiwamu – Going to HAM6 area to check S/Ns on electronics 16:41 (09:41) Kiwamu – Out of LVEA 16:43 (09:43) Jim B. – Finished with H0EPICS restart 16:45 (09:45) Cintas – On site to service rugs and garb 16:50 (09:50) Ed – Going to End-Y to terminate cables in the VEA 16:59 (09:59) Bubba – Back from Mid-X 17:05 (10:05) Christina & Karen – Finished at End-X and are going to End-Y 17:06 (10:06) Kyle – Back from the End Stations 17:10 (10:10) Filiberto – Out of the LVEA 17:18 (10:18) Hugh – Going to both End Stations to check HEPI pumps 17:45 (10:45) Hugh – Finished with HEPI checks at End Stations 17:50 (10:50) Hugh – Checking CS HEPI pumps 17:58 (10:58) Hugh – Finished with CS HEPI pump checks 18:04 (11:04) Nutsinee – Going to LVEA to take pictures near HAM4 18:13 (11:13) Nutsinee – Out of the LVEA 18:44 (11:44) Vendor on site to deliver drinks 18:54 (11:54) Gerardo – Going to End-Y VEA to measure for EitherCat cables 19:29 (12:29) Gerardo – Back from End Stations 19:49 (12:49) Manny & Leslie – Going into the LVEA to brackets for access sys on IO cabinets 20:27 (13:27) Bubba – Going into LVEA to look at N2 LTS system 20:28 (13:28) Gerardo – Going to Mid-Y to shim CP3 and CP4 20:58 (13:58) Bubba – Out of the LVEA 21:04 (14:04) Manny & Leslie – Finished in the LVEA 21:11 (14:11) Sheila & Jeff – Adjusted the ALS wrong polarization from 43% to 7% 22:10 (15:10) Sheila – Going to End-X 22:20 (15:20) Manny & Leslie – Going to both End Stations to install access controls bracket 22:39 (15:39) Chandra – Going into the LVEA to the walkover bridge 22:45 (15:45) Chandra – Out of the LVEA 22:48 (15:48) Chandra – Going to both end stations to make measurements 22:48 (15:48) Gerardo – Going into the LVEA – climbing around HAM6 End of Shift Summary: Title: 05/10/2016, Day Shift 15:00 – 23:00 (08:00 – 16:00) All times in UTC (PT) Support: Incoming Operator: Cheryl Shift Detail Summary: Maintenance Tuesday. Work continues on recovery of the PSL.