Reports until 16:14, Thursday 28 October 2010
X1 SEI
jeffrey.garcia@LIGO.ORG - posted 16:14, Thursday 28 October 2010 (271)
Ops Day Summary
Today's Activities:

Mid-Y activities - Kyle, Jodie, and others - venting of BSC 6 at Mid-Y.

Michael R. making PSL measurements in LVEA
~14:45 local – contractor on-site for PSL flooring quote

Corey and Betsy using crane near HAM1 and H1 PSL

Filiberto, Richard, and contractors dismantling H2 racks

Ski, Mike L. in LVEA  - taking apart the old H2 PSL table enclosure

Removal of the test mass begins at Mid-Y BSC 6 (Doug Cook, others)

----

By 16:15 local, work continues at the Mid-Y BSC 6 for the removal of the test mass.