Displaying report 1-1 of 1.
Reports until 11:43, Thursday 19 May 2016
H1 General
filiberto.clara@LIGO.ORG - posted 11:43, Thursday 19 May 2016 (27298)
Installation of field cables for Newtonian Noise Array.

Per work permit 5885, we started pulling in the field cables for the Newtonian Noise Array. This involved work over HAM4 and north side of BSC2. Cables runs are as follows:

CER TCS-C1 Rack to SUS-R6 Rack

CER TCS-C1 Rack to TCS-R1

Remaing cables that need to be pulled-in are the ITM ESD cables.