Reports until 16:18, Monday 30 April 2012
LHO General
Link
corey.gray@LIGO.ORG -
posted 16:18, Monday 30 April 2012
(2730)
Day Ops Summary
BSC8
:
Jeff G & Vincent ran measurements on this system throughout the day.
BSC6
:
ISC Table was to be moved down from LVEA.
Jason entered chamber for some quick work (he said he'd only be ~5min or so)
PSL
:
Moving cabinets in the PSL House
Getting phones hooked up
Later in afternoon, Rick & PSL crew were setting up to Power Up the laser.
BSC3
:
Documenting of chamber state
Begin In Chamber Cleaning
Remove door (on Beer Garden side)
MISC
:
FMy front end restart (Dave & Garcia)
Checking of network settings on LVEA workstations (Jim B.)
T Vo started work on re-installing H2ITMy Optical hardware
Filiberto started work of moving location of Dust Monitor Interface Box