Displaying report 1-1 of 1.
Reports until 16:43, Tuesday 01 May 2012
LHO General
jonathan.berliner@LIGO.ORG - posted 16:43, Tuesday 01 May 2012 (2736)
Tuesday Aft Ops Log
I relieved Corey at ~12:00 today, who was relieving someone else during the morning.
- Fire alarm maintenance was here in the afternoon.
- Apollo made a delivery for Hugh at ~13:55.
- EY: IAS, SEI, ALS, TMS, usual work. Phone communication still not working from the Control Room to EY (unclear if signal block is electronic or human in nature).
- BSC8: SLC, SUS working on finishing up BSC8 ITM, FM installation. We should work on keeping a camera pointed at BSC8 because the Control Room receives many inquiries regarding the status of work at BSC8.
- LVEA dust monitors not working for much of the day.
- AEI group continues working at PSL.
- Ops: Please give feedback to Cheryl.
- OSB doors locked at 16:05.
Displaying report 1-1 of 1.