Displaying report 1-1 of 1.
Reports until 16:28, Tuesday 24 May 2016
H1 SUS
filiberto.clara@LIGO.ORG - posted 16:28, Tuesday 24 May 2016 (27360)
CDS Electronics Activies

1. Ran field cables for the ITM ESD install. This required working on top of HAM3 to dress cables. Cables in the CER were dressed into SUS-C6.

2. Installed railing and shelves for the high voltage ESD supplies (CER Mezzanine)

3. Ken ( K Electric) ran power cable from CER Mezzanine to the SUS racks in the beer garden

4. Started installation of NGN electronics in CER Rack OAF-C1

5. Looked at power distribution for the Op Lever in LVEA. Power supply in CER was powered on, and began testing drop off points on the floor, correct voltage output.