H2 INS
corey.gray@LIGO.ORG - posted 11:09, Friday 29 October 2010 (274)
Payload Removed From BSC6 SEI (at Mid Y)
(Betsy, Corey, Mitchell, Travis)
Today we finished off the removal of objects from the BSC6 Optics Table.  Yesterday we removed the ETMy Optic Assembly, and some of the Transmission Monitor Telescope.  Today, we removed the rest of the Telescope, weights (hockey pucks), and all the tooling needed to remove the ETMy.

Additionally, the ribbon cable for the ETMy OSEMs was unbolted from the table and stuffed up and inside the Optics Table (to ease in the removal of the iLIGO BSC SEI system); want to note that this cable is still connected to the electrical feedthrough and should be disconnected as well.

The door is still removed (for later de-install work), and Filiberto left a power supply out there for the BSC6 illuminator.