PSL installation team April, 27th - Craned PSL oscillator, amplifier, gantry crane and others over from the H2 LAE to H1 LAE (see photo). - Beckhoff up and running. - Cabeling at the PSL racks next to the enclosure is ongoing. April, 30th - replaced all four water filters (those underneath the optical table and the ones at the chiller returnes). All of them are 10 µm filters now. - removed lifting frame from the oscillator box and mounted the oscillator, the mopa and the DBB to the optical table. - Put the new cabinets into the H1 ante-room and moved stuff (spare components / PSL components) over from the H2 ante room May, 1st - moved/cleaned one of the cabinets from H2 ante room, because we needed one more for the H1 ante room. It contains the spare HiPoPMC et al. - MOPA turned on and aligned (output 33.9 W) - all spare components and components from the "old" optical table are now inside the H1 LAE (this includes the high power PMC / ISS box) - started to put optis on the laser table - characterized fiber bundles for the high power oscillator: two fiber bundles (#2,#3) are already reassembled to the oscillator. Fiber bundle #1 has been cleaned twice. - removed the 4f lenses and the laser crystals from the oscillator as preparation for the pre-alignment procedure.